Byers Street Tunnel Repairs June 18 2
 

 What's Happening Now?

 

June Project Update: Byers Street Ahead of Schedule

New Street Tunnel work began June 29

Due to favorable spring weather, the Byers Street portion of the Downtown Tunnel Repairs project is moving ahead of schedule.

While crews wait for off-site concrete structures to cure for the Byers Street tunnel, they will begin working on the New Street Tunnel. This allows the contractor to maximize good weather and keep the overall project on track. 

Byers Street is on track for completion in mid August.

Project Overview

The City of Staunton is undertaking a critical infrastructure project to repair the aging stormwater tunnels beneath Byers Street, West Johnson Street, and New Street. Addressing these conditions now is essential to prevent structural failure and ensure public safety in the Wharf District.

  • Duration: February 2026 – Spring 2027

  • Investment: $4.62 Million

  • Goal: Restore structural integrity of tunnels supporting roadways while maintaining downtown access.

  • Method: "Top-down" construction to to remove and replace tunnel roofs and walls

  • Three priority locations under roadways:

    • Tunnel beneath Byers Street
    • Tunnel beneath New Street
    • Tunnel beneath West Johnson Street
Overall Map of Work Areas for the downtown tunnels. Purple highlights are on West Johnson and Byers Street and a blue highlight is on New Street where repairs will be performed.
Byers Street (Currently Underway)
New Street (Start June 2026)
West Johnson Street (Projected 2026-2027)
Project Background
FAQs
Parking

Tunnel Repairs Progress

Updated on 06/18/2026 4:18 PM

This album shows the progress of the Downtown Tunnel Repairs Project

Creek Tunnel Assessment Photos

Updated on 09/19/2025 12:26 PM

Photos of creek tunnels from structural survey showing deficiencies

Looking Ahead: Long-term Creek Considerations

These tunnel repairs are separate from any future consideration of "daylighting" the creeks, opening the tunnels and exposing them to the surface. The city has allocated funding to study the feasibility of daylighting portions of the Wharf area, which would involve looking at different engineering approaches and costs. 

The current repairs focus on immediate structural safety needs and restoring full street functionality. Any future creek daylighting decisions would be made separately and would include extensive community input.